Project Scope:
This project, which began in January 2023, consisted of the construction of a new logistics precinct, including, but was not limited to, new flammable stores, non-flammable stores, coolstores, wastestores, Inwards Goods, logistics office, hardstand, carparks, security fencing, and landscaping. The completed design aligns with Callaghan’s focus of the project, which was to ensure that the physical storage of chemical and hazardous goods within Callaghan Innovation complies with safety regulations.

Maltbys Engagement:
Maltbys provided full Professional Quantity Surveying services, including both pre-construction and construction-servicing services.

Project Details:
Client: Callaghan Innovation
Sector:
 Industrial
 Lower North Island
Budget: $12.8M
Location: Lower Hutt